Signing a Non-Firm Grid Connection for a Data Centre

November 17, 2026

A data centre takes about two years to build. Firm grid capacity can take several more. A growing number of transmission operators offer a way around the grid reinforcement delays: connect now, on capacity that is not guaranteed 100% of the time, and reduce your draw when the grid is under stress. This is a non-firm connection agreement.

We read the non-firm connection contracts, tariffs and rules published by transmission operators across Europe and the United States. This piece covers what it takes to sign one, and how to size it right.

A standard offer is still the exception

Fewer than half of the grids we surveyed offer a standard non-firm agreement to new loads. Most of the others are designing one. Elsewhere, non-firm terms are negotiated project by project, with no published reference: a site has to know which terms to ask for.

What it takes to sign

Each agreement sets a firm and a flexible capacity for the site, usually from a connection study. In some designs, only the equipment the site declares as flexible can be curtailed. The site must be able to reduce its draw automatically when the operator's signal arrives. Many agreements are temporary: they run until the grid is reinforced, or for a fixed term, after which the site moves to firm service.

The terms to check

The firm and flexible split. No operator publishes a standard ratio; it is set site by site. The firm part is what the developer can guarantee to tenants at all times.

Notice. Where it is published, notice is a few minutes at most, and often there is none. Reductions have to be automatic.

Limits on reductions. Most agreements set no limit on the number or length of reductions. Where a limit exists, it applies to annual energy or to a share of hours.

Expected hours. The contract rarely says how often a site will be curtailed: that depends on the local grid. Published design targets and modelling range from a few hours to over 200 hours a year, so it has to be estimated site by site, before signing. Nodera's technology anticipates how many hours of congestion a site should expect each year.

Duration and compensation. Check when the agreement ends and how the site moves to firm service. On standard terms, reductions are not paid; at best the site gets a lower grid tariff, and compensation can be negotiated.

In operations: anticipating grid curtailment

Grid operators give a few minutes of notice at most. Whatever equipment or technique a site uses to reduce its draw, it needs to see grid stress coming earlier than that.

Nodera forecasts grid stress at a site's connection point 72 hours ahead. A proprietary power flow model, combined with forecasts of local generation and consumption, models both system imbalance and local congestion at the node. The forecast can drive any flexibility equipment on site.